SL No. | Narrations | Details | |||
---|---|---|---|---|---|
1 | Name of scheme | Bulk Water Supply Scheme - Pulpally Grama Panchayath | |||
2 | Operation and maintenance | SLEC-SCHEME LEVEL EXECUTIVE COMMITTEE | |||
3 | Society Registration number & year | WYD/CA/338/2014 | |||
4 | Source of funding | World Bank & Jal Jeevan Mission | |||
5 | Year of commissioning | 2017 | |||
6 | Number of beneficiary households | Total | General | SC | ST |
At the time of commissioning | 2193 | 1349 | 83 | 761 | |
After commissioning | 2756 | 89 | 815 |
A | Distribution system | ||||
---|---|---|---|---|---|
1 | Total length Coverage | 349 Km | |||
2 | Diameter | 25 mm to 300 mm | |||
B | Existing design supply details | ||||
1 | Design supply rate | 70 lpcd | |||
2 | Total daily demand | 1.5Mld as per Mou |